I-805 HOV/Managed Lanes-South (SR54 to SR94)

Description: In and near San Diego and National City from 0.5 mile North of Route 805/54 separation to 0.2 mile North of Federal Blvd. UC. Construct High Occupancy Vehicle lane in each direction.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City National City, San Diego
Zip Code
 
Senate District
40
Assembly District 79
Congressional District 51
 
Caltrans District
11
 
 
County/State Route San Diego 805
Postmile Begin/End 9.4 13.8
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (HOV)      4.4  
Lane Miles Added (Mixed)  4.4      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Ramon Martinez 619-688-2516   ramon.martinez@dot.ca.gov
Design (PS&E) Phase
Caltrans Ramon Martinez 619-688-2516   ramon.martinez@dot.ca.gov
Right of Way Phase
Caltrans Ramon Martinez 619-688-2516   ramon.martinez@dot.ca.gov
Construction Phase
Caltrans Ramon Martinez 619-688-2516   ramon.martinez@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$37,947 $-19,162 $18,785
Non-bond Funding
State/Federal*
$244 $0 $244
Local**
$14,902 $2,570 $17,472
 
Total**** $53,093 $-16,592 $36,501

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$7,754 $0 $7,754 $3,933
Design(PS&E)
$4,000 $0 $4,000 $2,078
Right of Way
$0 $0 $0 $0
Construction
$41,339 $-16,592 $24,747 $23,767
 
Total* $53,093 $-16,592 $36,501 $29,777

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/30/2007 

06/22/2011 
 

 
05/30/2007 

06/22/2011 
100  05/30/2007 

06/22/2011 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2009 

11/30/2011 
 

 
11/01/2009 

11/30/2011 
100  11/01/2009 

11/10/2011 


Begin Right of Way Phase

End Right of Way Phase
 

08/01/2011 
 

 
 

08/01/2011 
100   

08/01/2011 


Begin Construction Phase

End Construction Phase
03/30/2012 

07/30/2014 
 

 
03/30/2012 

07/30/2014 
100  03/27/2012 

12/20/2013 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
100  04/01/2017 

11/01/2017 


Corridor System Management Plan
Adoption Date 08/09/2010    08/09/2010  08/09/2010 
Implementation Date 08/09/2010    08/09/2010  08/09/2010 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (HOV) 4.4
Lane Miles Added (Mixed) 4.4

Bond Funding Cost
Adopted:
$37,947,000
Current Approved:
$18,785,000
Actual Expenditures:
$18,785,000

 

Status as of December 31, 2023.