Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
I-805 HOV/Managed Lanes-South (SR54 to SR94) |
Description: In and near San Diego and National City from 0.5 mile North of Route 805/54 separation to 0.2 mile North of Federal Blvd. UC. Construct High Occupancy Vehicle lane in each direction.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Diego |
City | National City, San Diego |
Zip Code | |
Senate District |
40 |
Assembly District | 79 |
Congressional District | 51 |
Caltrans District |
11 |
County/State Route | San Diego 805 |
Postmile Begin/End | 9.4 13.8 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (HOV) | 4.4 | |
Lane Miles Added (Mixed) | 4.4 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Ramon Martinez | 619-688-2516 | ramon.martinez@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Ramon Martinez | 619-688-2516 | ramon.martinez@dot.ca.gov | |
Right of Way Phase |
Caltrans | Ramon Martinez | 619-688-2516 | ramon.martinez@dot.ca.gov | |
Construction Phase |
Caltrans | Ramon Martinez | 619-688-2516 | ramon.martinez@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$37,947 | $-19,162 | $18,785 | ||||
Non-bond Funding | |||||||
State/Federal* |
$244 | $0 | $244 | ||||
Local** |
$14,902 | $2,570 | $17,472 | ||||
Total**** | $53,093 | $-16,592 | $36,501 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$7,754 | $0 | $7,754 | $3,933 | |||
Design(PS&E) |
$4,000 | $0 | $4,000 | $2,078 | |||
Right of Way |
$0 | $0 | $0 | $0 | |||
Construction |
$41,339 | $-16,592 | $24,747 | $23,767 | |||
Total* | $53,093 | $-16,592 | $36,501 | $29,777 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
05/30/2007 06/22/2011 |
|
05/30/2007 06/22/2011 |
100 | 05/30/2007 06/22/2011 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
11/01/2009 11/30/2011 |
|
11/01/2009 11/30/2011 |
100 | 11/01/2009 11/10/2011 |
0 1 |
|
Begin Right of Way Phase
End Right of Way Phase |
08/01/2011 |
|
08/01/2011 |
100 | 08/01/2011 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
03/30/2012 07/30/2014 |
|
03/30/2012 07/30/2014 |
100 | 03/27/2012 12/20/2013 |
0 7 |
|
Begin Closeout Phase
End Closeout Phase |
|
|
|
100 | 04/01/2017 11/01/2017 |
0 0 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 08/09/2010 | 08/09/2010 | 0 | 08/09/2010 | 0 | ||
Implementation Date | 08/09/2010 | 08/09/2010 | 0 | 08/09/2010 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (HOV) | 4.4 | |
Lane Miles Added (Mixed) | 4.4 |
Bond Funding Cost | |
---|---|
Adopted: |
$37,947,000 |
Current Approved: |
$18,785,000 |
Actual Expenditures: |
$18,785,000 |
Status as of December 31, 2023.